Rampal Power Plant Project,Bangladesh
Project Profile
Name: Bangladesh Rampal Power Plant
Location: Khulna Rampal, Bangladesh
Method: DC
Construction duration
From: 2018.03
To: 2021.06
The site soil of Rampal power plant in Bangladesh belongs to filling soil, and the soil moisture content is large and loose.The ground of the road, AOG, coal yard and parking lot of the factory is treated by dynamic compaction(DC), and the result is remarkable after treatment.